Leguan’s new water plant opens, with mains expansion still ahead

Aerial file view of West Bank Demerara settlements, fields and riverfront.

File image: West Bank Demerara; the Leguan water plant is not pictured.

Leguan’s new water treatment plant was commissioned on Sunday, 22 November, bringing a reported two million litres of daily treatment capacity to the Essequibo island. The investment is put at approximately G$700 million, with roughly 3,300 residents expected to benefit, according to DPI’s report of the commissioning.

The plant is a completed step in the island’s water programme, not the end of the network works. Guyana Water Incorporated chief executive Shaik Baksh said further transmission lines would be installed from January to improve pressure and extend treated-water delivery.

The wider investment predates Sunday’s ceremony. In July 2023, the Caribbean Development Bank approved a US$76.2 million loan for Guyana’s Water Supply Improvement Project. Its original scope combined treatment plants and storage with transmission mains and meters, covering several coastal service areas, including Leguan and Wakenaam. Nearly 15,000 households were expected to benefit across that wider programme—not on Leguan alone.

Two islands, one plant contract

The published award notice for the Leguan and Wakenaam plants gives a more precise view of the construction package. Lot 2 was awarded to a joint venture of Sigma Engineers Ltd and Hebei Wansheng Environmental Protection Engineering Co. Ltd for G$1,486,448,800.

That contract covers two treatment plants with a combined capacity of four million litres a day. It lists a commencement date of 13 November 2024 and an 18-month duration. The notice expressly identifies Lot 2 as financed by the Government of Guyana, rather than by the bank.

The award record separates this government-financed construction package from the broader CDB loan. It gives no island-by-island breakdown of the joint price or certified final expenditure. Leguan’s approximately G$700 million commissioning figure cannot be reconciled with the two-island award simply by dividing the contract value in half.

GWI’s August 2026 procurement statement also identifies Sigma Engineers as the contractor for Leguan and Wakenaam. The original award supplies the joint scope, financing source and contract period behind that description.

The pipes come next

Baksh’s commissioning remarks referred to new eight-inch transmission lines beginning in January. The CDB-hosted notice for a separate Leguan mains tender describes approximately 4.4 kilometres of 150-millimetre PVC pipe. It identifies GWI as the executing agency and records an October 2026 closing date.

The documents do not establish that the tendered section and the eight-inch works described on Sunday are identical. A procurement notice is also not an award or proof that installation has begun. The route, contractor and delivery timetable for the next phase would give households and businesses a clearer account of when pressure improvements should reach their area.

In its October account of national infrastructure work, GWI listed Leguan alongside additional plants at Maria’s Delight, Wakenaam, Bath and Adventure. The utility acknowledged continuing concerns about iron in some groundwater supplies. Its programme therefore involves improving the water already reaching customers, as well as extending connections.

For a household or shop buying drinking water, treatment can affect a recurring expense. CDB’s 2023 explanation of the programme identified that cost, and the time spent cleaning items affected by untreated supply, as burdens for residential and commercial users. The expected savings formed part of its case for investment; the commissioning report provides no measurement of savings achieved on Leguan.

President Irfaan Ali linked the island’s water and electricity services to the prospect of agro-processing. A water-refilling station was also proposed. Both remain plans. Leguan’s households, shops and producers now have a commissioned treatment plant, with the next phase of pipe works intended to improve how that water reaches them.